Project Details

Zoom

1,100

hectares landholding

Alt text: Aerial view of Middle Arm Precinct showing road network, site access and early-stage development works
Aerial view of Middle Arm Precinct showing subdivided land, earthworks and surrounding bushland
Middle Arm Precinct
Visit Project Website

On this page

Middle Arm Precinct is a Northern Territory Government initiative to transform Middle Arm into adevelopment-ready industrial precinct within Darwin Harbour.

Project Type
Industrial
Project stage
Underway
Timeline
2021–2026

About the project

The precinct is proposed across approximately 1,500 hectares (15 square kilometres) and is being master planned to enable coordinated industrial development through shared common-user infrastructure and a clear approvals and environmental assessment pathway.

The master-planning program is informed by more than 200 technical studies and a strategic assessment approach to guide long-term development. The precinct is intended to attract industries aligned with the Territory’s future economy, including hydrogen, carbon capture, advanced manufacturing and minerals processing.

Middle Arm already supports nationally significant energy and industrial operations. Current investment within the precinct includes:

  • Santos Darwin LNG (site 7682-08) — a leading Australian oil and gas exploration and production company operating in the Northern Territory.
  • INPEX Ichthys LNG Darwin (Middle Arm Precinct 7) — Ichthys LNG produces 8.9 million tonnes of LNG and 1.65 million tonnes of LPG per annum.

A Land Allocation Framework supports strategic land use aligned to the precinct plan and strategic objectives. It provides a structured process to evaluate proposals against strategic and economic benefit, and opportunities to maximise integration and collaboration across the precinct.

While projects will continue to progress through commercial development, the framework can provide proponents greater certainty about land requirements to support planning. All projects remain subject to approvals, community consultation and all regulatory and administrative requirements, including Environment Protection Authority processes.

Land Development Corporation supports precinct delivery by unlocking and preparing strategic land and progressing investment-ready pathways within a whole-of-government framework.

Timeline

2021

Added to Infrastructure Australia’s National Infrastructure Priority List.

Complete

2022

Strategic Assessment Agreement signed with Territory and Commonwealth regulators.

Australian Government committed more than $1.5b (planned equity) for shared enabling infrastructure.

Complete

2022–23

NT Government committed $27m for environmental studies, planning and project development.

Complete

2025–26

Ongoing proponent engagement and land allocation progression under the endorsed framework; activation planning for a battery storage site continues

Complete

Beyond 2026

Staged land allocations and enabling infrastructure delivery aligned to proponent readiness

Underway